The background
Project management is playing an increasingly critical role
in today’s rapidly changing business environment. Delivering
products or services on time and within budget - without sacrificing
quality - is now a matter of survival as much as gaining a
competitive advantage. With the pressure increasing, companies
across many industries recognise that time is one of their
most valuable resources and investing in project management
solutions will help make the most of their potential.
Effective project management has always been essential for
major construction projects and complex manufacturing operations.
Few projects are as complex as building the Space Shuttle,
NASA’s flagship manned space vehicle. Although the Space
Shuttle is famous as the world’s first reusable space
vehicle, only part of the complete structure is recyclable.
The external fuel tank, the largest part of the Space Shuttle
system, is jettisoned after use and allowed to break up in
the atmosphere over a remote ocean area. A new external fuel
tank is needed for each Shuttle launch.
Lockheed Martin Space Systems Company, Michoud Operations
at NASA’s Michoud Assembly Facility in New Orleans,
Louisiana, builds the External Tank (ET). A huge structure,
47 meters long and 8.4 meters in diameter, holds over two
million litres of cryogenic propellants that supply 3,900
litres of fuel per second to the Shuttle’s three main
engines. It also forms the main structural backbone to the
Shuttle, absorbing most of the thrust on takeoff. Manufactured
in one of the world’s largest buildings - covering almost
17 and one half hectares under one roof - the completed tank
is so enormous that it has to be shipped by barge to its launch
destination in Florida.
The challenge
Until recently, Lockheed Martin - which has
been making the fuel tanks for over a quarter of
a century – created
the master production schedule using limited automated
methods.
 |
 |
When
we looked at project management packages,
we evaluated many and concluded that most
could not accommodate the complicated nature
of our project |
|
 |
 |
|
 |
In the past few years, the development of sophisticated project
management software has revolutionised the labour-intensive
world of scheduling. Ms. King-Dillon started to look for an
alternative to make the planning process more efficient.
“Although I had previously generated master plans electronically,
there were too many variables and I found it both faster and
easier to make the schedules using standard methods. When
we looked at project management packages, we evaluated many
and concluded that most could not accommodate the complicated
nature of our project.”
The solution
The solution came from project management specialists Asta
Development, a UK based company. Asta’s PC-based project
management tool Powerproject, used by over 30,000 companies
worldwide, is designed to combine powerful features with simplicity
and speed - particularly when dealing with complex projects
involving many tasks.
Teresa King-Dillon is delighted with the system. “This
is the only package I found which allows me to schedule multiple
tasks on a single bar, as well as providing additional benefits.
Powerproject demonstrates visually the implications in time
and resources when a new task is added. With other software,
we spent a lot of time just re-sequencing the schedule to
get it to work - Powerproject lets us experiment as much as
we like with ‘what if’ scenarios to provide a
better solution.”
 |
 |
This
is the only package I found which allows me
to schedule multiple tasks on a single bar,
as well as providing additional benefits. |
|
 |
 |
|
 |
Ms. King-Dillon also discovered that by using this software,
workflow management is also more effective. “The automatic
time analysis function warns us if we are going to have a
work station resource overload. When challenging events occur,
I can tell within minutes exactly how it’s going to
impact the schedule. Before, we did not have the capability
to do that as quickly.”
Powerproject has taken a lot of the work out of reporting
progress to management. “We’re able to give management
accurate, automatic updates on a weekly / daily basis, as
required. They can now easily get a snapshot of where each
project is, in real time.”
Lockheed Martin has found technical support to be outstanding
despite the fact that Asta’s technical team is based
in a different continent. “Asta’s technical support
people are awesome. What I want to do may seem idiosyncratic,
but the support team always finds unique and creative ideas
to help.”
The only difficulty that Ms. King-Dillon encountered is Powerproject’s
high upper limit of 127 task segments per stage, an area that
needed to be customised by Asta to meet Lockheed Martin’s
particular requirements. “The Master Schedule encompasses
more than 5000 activities across 85 major workstations.”
Lockheed Martin has moved on to Asta Development’s
latest and more advanced project management tool, Asta Powerproject
– a new solution that has no limits on the size or complexity
of projects.
“Asta Powerproject has totally changed the way we do
business in Master Scheduling,” says Ms. King-Dillon.
“It greatly enhances our master scheduling process.”
|