Mace uses Asta Powerproject to build the
London Eye
The challenge
Few deadlines in recent times have loomed as large as the
turn of the Millennium. For internationally renowned professional
management company Mace (www.mace.co.uk),
finding an effective project management solution was vital
when it was asked to supervise construction of the London
Eye, a major UK Millennium project that has won unqualified
approval from critics and the public alike.
The biggest observation wheel in the world, the London Eye
is also one of the tallest structures in London. At 135 metres,
it towers over St Paul's Cathedral and Big Ben.
Building such a large and complex structure
was an unprecedented challenge for all involved. Mace was
called in to co-ordinate the construction, an architectural,
engineering and logistical feat involving seven major contractors
from around the world.
 |
 |
We
encouraged all our contractors to use the
Asta Powerproject system for day to day planning, |
|
 |
 |
|
 |
"At the outset, there were two basic choices for how
to handle the construction," says Raj Chaman, planning
manager for the London Eye project at Mace. "The wheel
could have been built from the bottom up at its site in Jubilee
Gardens. The second option was to build as much as possible
away from the site and then assemble it on site in the final
stages. In order to minimise disruption for those living and
working in the area, the second option was chosen. That meant
that we had to co-ordinate the design, manufacture and assembly
of the wheel's many different components at several locations
across Europe, then ensure that they were transported safely
to their final destination."
"The plan was to winch the wheel slowly
into an upright position once it was put together, but as
was widely reported at the time, we hit some snags during
the uplift process. Despite this, we managed to hit the December
31st deadline," said Raj Chaman.
In addition to the major task of assembling
the wheel itself, there were associated works on the project
such as the landscaping of the grounds at Jubilee Gardens
and the construction of a new pier to receive visitors arriving
by river.
The solution
 |
 |
Using
Asta Powerproject, it was relatively simple
to reschedule the rest of the work |
|
 |
 |
|
 |
"We encouraged all our contractors to use the Asta Powerproject
system for day to day planning," said Raj Chaman. "As
well as helping us to co-ordinate all the disparate tasks
as the time for final assembly drew near, we found that it
made communication and exchange of ideas between everyone
involved very much easier. A particularly useful feature was
the ease with which Asta Powerproject could pull all the latest
developments together into an up-to-date colour presentation.
Since reporting and presenting progress to a number of different
teams was an important and regular requirement throughout
the project, it was good to be able to run off up-to-the-minute
status reports at any time."
Asta Powerproject's finest hour, however, came
when the uplift of the wheel to its final vertical position
did not go as smoothly as planned.
"We had problems with one of the temporary
cables and had to abandon the first attempt. This meant that
all subsequent tasks had to be resequenced if we were to meet
the Millennium deadline. Using Asta Powerproject, it was relatively
simple to reschedule the rest of the work to ensure that if
nothing else went wrong, we would be able to hit the completion
date."
In the event, the London Eye was operational
on schedule and seems destined to become a familiar part of
the London skyline for many years to come.
|